An aerial view of a transformer set on its concrete base alongside its kiosk within a fenced compound, at a renewable energy site in West Northamptonshire.
52.2°N · UK-wide Self-delivered civils
Civil Engineering

Transformer, Utility & DNO Infrastructure

The contestable works that get a site connected — DNO trenches and ducting, cable routes and terminations, earthing systems, RMU housings and the crane lifts that set the units. Self-delivered, and coordinated with the DNO.

Get in Touch
Overview

Infrastructure for grid connection

Getting a renewable site energised depends on the infrastructure that connects it to the network — the transformers, switchgear, earthing and cabling that move power safely from generation to grid. Building it is specialist civil and groundwork, and it sits on the critical path to energisation.

Much of it is work HWBC can take on directly — so it doesn’t sit waiting in the DNO’s queue.

Getting a renewable site energised depends on the infrastructure that connects it to the network — and much of that work is contestable: the parts of a grid connection a developer can have built directly, rather than waiting on the Distribution Network Operator (DNO) to do them. It covers the civils and infrastructure up to the DNO’s point of connection.

HWBC self-delivers those contestable works: DNO trenches and ducting, cable routes and terminations, earthing systems, RMU and switchgear housings, and the crane lifts that set the units — coordinating with the DNO throughout so the connection lands on programme.

With our own workforce, plant and machinery, we take this work from first groundworks through to connection support.

What we deliver

The contestable works

The parts of a grid connection we build directly — up to the DNO’s point of connection.

01

DNO Trenches & Ducting

Excavation, ducting and reinstatement for the DNO cable route — the contestable trenching that carries the connection to the point of supply.

02

Cable Routes & Terminations

HV and LV cable corridors, draw pits and joint bays, through to cable entries and terminations at the units.

03

Earthing Rings & Mats

Earthing systems around the units — earthing rings, earth mats, rods and conductor installation, with the associated excavation works.

04

RMU Units & Special Housings

Setting ring main units and switchgear, and constructing the special housings and enclosures that protect them.

05

Crane Lifts

Preparing crane pads and managing the lifts that set transformers, RMUs and switchgear safely onto their bases.

06

DNO Liaison & Coordination

Liaising with the DNO throughout the contestable works, so the build meets their requirements and the connection lands on programme.

The electrical scope

DNO connection & control rooms

DNO Connection & Liaison

Built to the standard the DNO requires

The contestable works still have to satisfy the Distribution Network Operator — so the trenching, ducting, earthing and cable entries are built to their requirements. HWBC delivers that DNO-side infrastructure and liaises with the DNO and the wider project team throughout, so the connection is ready when its slot comes and energisation stays on programme.

Two HWBC operatives installing an earthing system in a trench, with a transformer and green DNO connection cabinet behind, at a renewable energy site in West Northamptonshire. Earthing & DNO · West Northamptonshire
Self-Contained Control Rooms

Concrete base to fitted-out building

Beyond the foundations and the compound, HWBC constructs the self-contained control room buildings that house a site's electrical heart — the inverters, switchgear and distribution boards. We build the structure and fit it out, including specialist GRP grating floor systems that give safe access over the cable voids below while letting cabling run cleanly beneath the equipment.

One in-house team takes the electrical infrastructure from the concrete base through to a finished building ready for commissioning.

Three SMA Sunny Highpower inverters wall-mounted on unistrut inside a self-contained control room built by HWBC, with a specialist GRP grating floor. Control room · GRP grating floor
How we work

Three stages to connection

01

Plan & coordinate

Work through the connection design, foundation loads and DNO requirements with the project team.

02

Build & install

Construct foundations, compounds, earthing and control rooms; prepare crane pads and support the equipment lifts.

03

Connect & support

Install cable infrastructure, tie in the DNO connection, and support the works through to energisation.

Proof on the ground

Recent works

Cambridgeshire

Combined switchgear & transformer base

HWBC built the reinforced concrete foundations for a combined switchgear and transformer unit — rebar cages and column formwork through to the finished base with cast-in duct entries — then prepared and supported the crane lift that set the unit in place.

A completed reinforced concrete base with cast-in duct entries, built to receive a combined switchgear and transformer unit, at a renewable energy site in Cambridgeshire.Finished base
A mobile crane setting a combined switchgear and transformer unit onto its concrete base, with two HWBC operatives guiding the lift, at a renewable energy site in Cambridgeshire.Setting the unit

Need transformer, utility or DNO infrastructure for your next connection?

Call 01327 830423
Get in Touch